ONE
PRE-AGREEMENT PHASE
INTERVIEW & INITIAL DISCUSSIONS
The first step is the most important where we discover the essential criteria of the client's project; the who, what, when, where, and why
-
What are the client's requirements as well as the look and feel, style, vision, expectations, scope, experience etc.
-
Are the architect's abilities and goals suitable and what professional services will be provided
-
What type of project and what type of project delivery is expected
-
What consultants may be required
-
What is the client's expectations regarding budget & timeline
-
What approvals are required from authorities having jurisdiction
-
Open discussion of concerns
TWO
PRE-AGREEMENT PHASE
INFORMATION GATHERING & DOCUMENTATION
-
Review the survey provided by the client
-
Review zoning restrictions
-
Preliminary review of the site, perhaps a site visit
-
Evaluate the budget if provided
-
Re-evaluation of program, schedule. budget etc
-
Preliminary construction cost estimates
-
Review production schedules and application milestones
-
Ultimately leads to a decision of whether to proceed with this partnership
-
leads to a fee agreement
-
THREE
SCHEMATIC DESIGN PHASE
-
Obtain legal survey from client for review
-
Review of preliminary space requirements
-
Production of site plan, floor plans, sections, elevation, studies etc. for client review
-
Selection of materials, finishes, fixtures
-
Adjustments to design drawings per client's comments
-
Finalize consultant agreements (structural, mechanical, electrical, civil, etc)
-
Obtain any necessary testing requirements
-
Determine systems to be used
-
Obtain estimate of cost for major system/components
-
(ex: steel or concrete)
-
-
FOUR
DESIGN DEVELOPMENT PHASE
-
Coordination with consultants (structural, mechanical, electrical, civil, etc.) to update drawing packages
-
coordinate specialized systems (security, vacuum, lighting etc)
-
obtain/review estimate of costs for specialized systems for client review
-
-
Update site plan, floor plans, elevations, sections with further detail and information
-
Review/approval of materials, finishes, fixtures
-
Prepare preliminary or outline specifications
-
Update estimate of construction cost
-
Preliminary review of potential general contractors
-
Application for any relevant jurisdictions
-
site plan approval
-
rezoning
-
committee of adjustments
-
FIVE
CONSTRUCTION DOCUMENTS PHASE
-
Preparation of IFC (Issued for Construction) drawing package including coordinated consultants' drawings
-
Schedules, specifications, details, labelling of materials/finishes
-
Determine items/work to be furnished by the client, not to be in the construction contract
-
Determine with client preferred procedure of GC selection:
-
direct selection
-
invited bidding
-
open bidding
-
-
Stamp documents for building permit application and tendering
SIX
BIDDING & NEGOTIATION PHASE
-
Assist the client through selected bid process
-
Issue documents to bidders
-
Hold bid meetings and site tours as required
-
Receive, open, tabulate, and analyze bids as per procedure established with client
-
Selection of successful bidder and notification of unsuccessful bidders
-
Assist the client and contractor in execution of construction contract
SEVEN
CONTRACT ADMINISTRATION PHASE I
-
Obtain and review the GC's construction schedule
-
Construction begins
-
Review of shop drawings and samples
-
Assist with applications for gas, water, electricity, telephone, etc
-
Attend site meetings
-
Perform periodic field review reports to observe and verify compliance and conformity with contract documents
-
Consultants' field reviews and respective reports during construction progress
-
Provide answers to site questions/interpretation of contract documents
-
Issue Supplementary Instructions and Change Orders when necessary
-
Review and issue Certificates for Payment based on evaluation of work performed and materials supplied in relation to the contractor's progress application
EIGHT
CONTRACT ADMINISTRATION PHASE II
-
Arrange for appropriate personnel to attend demonstration of systems and obtain records
-
Contractor to provide application for Certificate of Substantial Performance
-
Deficiency lists to be addressed
-
Obtain and review documents for release of holdback monies
-
Issue Certificates for Payment for holdback release
-
Assist client in obtaining occupancy permit
-
GC to provide application for Statement of Completion
-
Obtain manuals, warranties, certificates of inspection etc from GC
-
Site visits to verify completion of respective trades and completion of project.
-
Issue final Certificate of Payment
-
Submit final invoices to client
-
Review any defects during one-year warranty period